The Schedule tab displays the start and end date for each package added to the project. Each newly created package is automatically added to the schedule.
Color-Coded by Tracking Status
The bar of each package on the timeline is color-coded to match the current tracking status.
Hover Information
Hovering over a package displays package details and the Tracking log. Click the package bar to open a new page with the package details.
Edit Schedule
A package's start date or end can be moved to a new start date if its progress is at 0% complete.
A package's end date can be moved even if progress has started.
An entire package can be clicked/dragged to change the start and end date if its progress is at 0% complete.
Package start and end dates are independent and must be individually adjusted.
A package cannot be split into more than one package with separate start and end dates.